Independently compiled cost-per-m² data for 8 project types across all UK regions. Based on live project data from Page Building Consultants — updated quarterly and freely available to cite.
Cost-per-m² figures, regional multipliers, trade breakdowns and labour rates reviewed against live project data.
|National average figures for England. Apply regional multipliers (see table below) to adjust for your location. All costs exclude VAT, professional fees, and planning charges unless stated.
| Project Type | Unit | Low | Mid | High | |
|---|---|---|---|---|---|
Single Storey Extension | per m² GIA | £1,800 | £2,400 | £3,200 | |
Two Storey Extension | per m² GIA | £1,600 | £2,100 | £2,800 | |
Loft Conversion | per m² GIA | £1,500 | £2,000 | £2,700 | |
New Build House | per m² GIA | £1,900 | £2,600 | £3,800 | |
Full Refurbishment | per m² GIA | £800 | £1,400 | £2,200 | |
Commercial Fit-Out | per m² NIA | £700 | £1,200 | £2,500 | |
Groundworks | per m² site area | £120 | £280 | £600 | |
Garage Conversion | per m² GIA | £900 | £1,300 | £1,800 |
All figures are national averages for England, excluding VAT (20%), professional fees (8–15%), and planning/building regulations charges. Costs reflect Q2 2026 market conditions. Click any row to expand detail.
Apply these multipliers to the national average cost-per-m² figures above to get a region-adjusted estimate. Based on BCIS regional indices and live tender data.
Adjusted totals update automatically
| Region | Multiplier | Adjusted Cost/m² |
|---|---|---|
London | 1.35× | £3,240/m² |
South East | 1.18× | £2,832/m² |
East of England | 1.10× | £2,640/m² |
South West | 1.05× | £2,520/m² |
West Midlands | 0.97× | £2,328/m² |
Scotland | 0.96× | £2,304/m² |
East Midlands | 0.95× | £2,280/m² |
North West | 0.94× | £2,256/m² |
Yorkshire & Humber | 0.92× | £2,208/m² |
Wales | 0.90× | £2,160/m² |
North East | 0.88× | £2,112/m² |
Northern Ireland | 0.85× | £2,040/m² |
Multipliers are indicative and based on BCIS regional tender price indices and Page Building Consultants live project data. Individual projects may vary. Last updated: .
Trade-by-trade breakdowns, current material price indices, and UK labour day rates — all updated Q2 2026.
| Trade / Element | % of Total Cost |
|---|---|
| Preliminaries & Site Setup | 8–15% |
| Substructure & Foundations | 8–18% |
| Superstructure & Frame | 12–20% |
| Roof | 8–14% |
| External Walls & Cladding | 6–12% |
| Windows & External Doors | 5–10% |
| Internal Partitions & Joinery | 4–8% |
| Mechanical & Electrical | 12–20% |
| Finishes & Decoration | 6–12% |
| Kitchens & Bathrooms | 5–15% |
All rates are indicative UK national averages for Q2 2026. Labour rates exclude employer NI, holiday pay, and plant. Material prices are supply-only ex-VAT. Actual costs will vary by project, location, and contractor.
Common questions about how to use and interpret UK construction cost benchmark data.
Ask a QuestionThese figures are based on live project data from Page Building Consultants, cross-referenced with BCIS (Building Cost Information Service) published indices and RICS guidance notes. They represent typical costs for standard specification projects in England and should be used as a starting point for budget planning, not as a substitute for a professional estimate. Actual costs can vary by ±20–30% depending on site conditions, specification, and contractor selection.
Benchmark data gives you a ballpark — a professional estimate gives you the number you can actually build to. Our estimators have 38 years of UK construction experience and deliver detailed, trade-by-trade cost plans within 24 hours.
Quotes from £255 · 24-hour turnaround · All UK regions covered